In brief
- File a federal TDY travel claim within 5 working days after the trip ends, or at most every 30 days on continuous travel, unless your agency sets a shorter limit.
- The agency must flag errors within 7 working days and pay a proper claim within 30 calendar days of submission to the approving official.
- A late payment fee runs from the 31st day at the Prompt Payment rate (4.75% for July–December 2026) or as a flat fee, plus any card late-charge equivalent; fees under $1.00 are not paid.
- The interest-type late fee is not W-2 wages, but the amount equal to a card late charge is reported as additional W-2 wages.
- The December 8, 2025 FTR rewrite kept the filing deadline and the late fee but renumbered both, so a memo or training slide written before that date may cite a section that now says something else.
- A claim still denied after agency reconsideration can go to the Civilian Board of Contract Appeals; the general limit for claims against the government is six years.
Three clocks start when the trip ends
A federal travel claim sits between three deadlines that run on different calendars. (The regulation's own term is "travel claim (voucher)"; the E-Gov Travel Service, or ETS, calls it an expense report.) You have a short window to file. Your agency then has a fixed number of calendar days to pay you. And if you charged the trip to an individually billed government travel card, the card issuer's statement cycle runs regardless of the other two. Most voucher problems come from treating these clocks as one.
The rules for the first two are in 41 CFR part 301-52, the claims part of the Federal Travel Regulation (FTR). GSA rewrote the whole FTR in a final rule published and effective on December 8, 2025. The substance of the filing deadline and of the late payment fee survived, but the section numbers changed, so a policy memo, training slide or website written before that date may cite a section that now says something else.
| Topic | Section before December 8, 2025 | Current section |
|---|---|---|
| Filing deadline (5 working days, or 30 days on continuous travel) | §301-52.7 | §301-52.1(a)(6) |
| Agency must pay within 30 calendar days | §301-52.17 | §301-52.7 |
| Agency notice of errors in the claim | §301-52.18 | §301-52.8 |
| Late payment fee entitlement | §301-52.19 | §301-52.9 |
| How the late payment fee is calculated | §301-52.20 | §301-52.10 |
| $1.00 minimum fee | §301-52.21 | §301-52.11 |
| Tax treatment of the fees | §§301-52.22–301-52.23 | §§301-52.12–301-52.13 |
| Penalties for fraud | §301-52.12 | §301-52.14 |
These rules apply to federal civilian employees on temporary duty (TDY) travel under chapter 301 of the FTR. Relocation claims under chapter 302 and military travel (see military TDY per diem) follow other rules.
When your claim is due
The filing deadline is in §301-52.1(a)(6). You must submit the claim within 5 working days after you complete the trip or the period of travel. If you are in continuous travel status, the requirement is "at most every 30 days," meaning no more than 30 days should pass between claims while the travel continues. Your agency can require a shorter timeframe administratively, so treat the FTR figure as the outer limit and do not count on it as a grace period.
The FTR glossary does not define "working day." For a standard Monday-to-Friday schedule, counting workdays and skipping federal holidays is the natural reading. If you work a compressed or alternative schedule, ask your travel office how it counts, and write the answer down.
Example: a trip ending the week of Thanksgiving
Say you return home on Thursday, November 19, 2026. Count the working days after completion: Friday, November 20 is day 1; Monday, November 23 is day 2; Tuesday, November 24 is day 3; Wednesday, November 25 is day 4. Thursday, November 26 is Thanksgiving Day, a federal holiday, so Friday, November 27 is day 5. The claim is due by November 27 unless your agency requires it sooner.
Example: a long assignment in continuous travel status
Take an assignment that runs from Monday, January 4, 2027 to Friday, March 26, 2027. Keeping each interval to 30 days or less means filing by Wednesday, February 3 and again by Friday, March 5, then filing the final claim within 5 working days after March 26. Your agency may fix its own cycle instead.
What happens if you file late
The claims rules attach no dollar penalty to a late claim, but lateness has consequences elsewhere. Your card bill is still due on its own schedule. More pointedly, an agency can normally collect undisputed delinquent card balances from your pay only after it has reimbursed you on a proper travel claim. It may collect anyway if you did not file a proper claim within the filing deadline and there are no extenuating circumstances. At the far edge, federal law generally requires a claim against the government to be received within six years after it accrues. That is a statute of limitations and should never be a filing window you plan around.
What makes a claim "proper"
The agency's 30-day payment deadline and your late payment fee both run from submission of a proper travel claim to the agency's designated approving official. A claim that lacks a required element can be returned, so completeness is the part you control. A proper claim contains:
- Receipts for every lodging expense, whatever the amount, and for any other expense over $75, together with an itemized list of expenses, the standard data elements and anything else your agency specifically requires. Telephone calls, transit fares and parking meter fees at the TDY location may be grouped into one total, but any individual item over $75 must be listed separately. The receipts guide covers these thresholds in more detail.
- The reduced daily rate, if your authorization set a reduced lodging or M&IE rate. With a reduced M&IE rate, the agency decides whether you must itemize meals.
- The type of leave and the number of leave hours for each day.
- The dates you arrived at and departed from the TDY station.
- Evidence of necessary expenses, including any special authorizations, such as an actual expense approval.
Several obligations sit next to the claim. You must account for any outstanding travel advance under agency procedures and submit unused tickets or other evidence of refunds. The claim must be filed in the format prescribed by ETS unless your agency has an exception from ETS use. An agency may exempt a confidential expenditure from the receipt requirement.
Receipts must be retained for 6 years under National Archives General Records Schedule 1.1, item 010. Ask whether your agency's system stores the receipt images for that period or whether you should keep copies yourself.
What the agency must do, and by when
Once you submit, the authorizing or approving official, or a designated representative such as your supervisor, reviews and signs the claim. The reviewer is expected to have full knowledge of your activities on the trip and to confirm that the claim is properly prepared, that a copy of the travel authorization is provided, that each type of expense is authorized and allowable, that the amounts are accurate and that required receipts, statements and justifications are attached. A certifying official then certifies the voucher before payment and, by statute, bears final responsibility for its validity.
Two deadlines bind the agency:
- 7 working days to flag errors. The agency must tell you, within seven working days after you submit, about any error that would prevent payment within 30 calendar days.
- 30 calendar days to pay. The agency must reimburse you within 30 calendar days after you submit a proper claim to its designated approving official. The deadline carries out the Travel and Transportation Reform Act of 1998, which requires reimbursement of a proper voucher within 30 days and a late payment fee when that deadline is missed.
The 30-day rule expressly excludes nine relocation allowances: moving and storing household goods and professional books, papers and equipment; moving a mobile home; shipping a privately owned vehicle; temporary quarters subsistence expenses; residence transaction expenses; the relocation income tax allowance; relocation services companies; home marketing incentive payments; and property management services. Ordinary TDY claims are fully covered.
| Event | Rule | Date |
|---|---|---|
| Proper claim submitted to the approving official | — | Monday, October 5, 2026 |
| Last day for the error notice (7 working days; Monday, October 12 is Columbus Day) | §301-52.8 | Thursday, October 15, 2026 |
| Last day to pay without a late fee (30 calendar days) | §301-52.7 | Wednesday, November 4, 2026 |
| Late payment fee begins to accrue (31st day) | §301-52.10(a)(1) | Thursday, November 5, 2026 |
How the late payment fee is calculated
If the agency does not reimburse you within 30 calendar days after a proper claim, you are entitled to a late payment fee. The entitlement is in §301-52.9, which is the section to quote if you ever have to ask for the fee. The agency has two ways to compute it:
- Prompt Payment Act interest: the prevailing Prompt Payment Act interest rate, applied from the 31st day after submission of the proper claim through the day payment is made; or
- A flat fee of not less than the prompt payment amount, based on an agencywide average of travel claim payments.
On top of either, the agency must add an amount equal to the late payment charge the card contractor could have imposed on you had you not paid your card bill. It compensates for the situation in which the agency's delay would otherwise have pushed your card account into late charges. A fee that computes to less than $1.00 is not paid.
Treasury's Bureau of the Fiscal Service publishes the Prompt Payment interest rate for six-month periods; the rate for July 1 through December 31, 2026 is 4.75%. The claims rules do not specify a day-count convention. Treasury's Prompt Payment rules for vendor invoices use a 360-day year, so the example shows both bases. The difference is a few cents.
| Item | Computation | Amount |
|---|---|---|
| Proper claim submitted | Monday, October 5, 2026 | — |
| Payment made | Tuesday, November 24, 2026 | — |
| Days of interest | November 5 through November 24 | 20 days |
| Interest on a 360-day year | $2,000 × 4.75% × 20 ÷ 360 | $5.28 |
| Interest on a 365-day year | $2,000 × 4.75% × 20 ÷ 365 | $5.21 |
| Card late-charge equivalent, assuming your cardholder agreement allowed a $25 late charge | Equal to that charge | $25.00 |
The two parts are taxed differently. The interest or flat fee is not reported as wages on Form W-2, because the IRS treats it as being in the nature of interest; the agency reports it under IRS guidelines. The additional amount equal to the card late charge is reported as additional wages on your W-2.
The regulation does not say how a claim returned for correction affects the clock. Because both the deadline and the fee are tied to a proper claim, keep your travel system's submission and return timestamps. If a payment arrives late without a fee, those records are what the finance office will need to check.
Advances, split disbursement and your card statement
If you received a travel advance, the claim is also where it is settled. When the advance is smaller than the amount due on the voucher, the agency deducts it and pays you the net difference; when the advance is larger than what you are owed, you must refund the excess immediately. If you are in continuous travel status or file periodic vouchers under one trip authorization, the agency may reimburse each interim voucher in full and deduct the advance only when the final voucher is filed.
Split disbursement changes where the money goes and leaves the amount you are owed untouched. The travel voucher reimbursement is divided between the charge card vendor and the traveler, with the balance owed to each sent directly to that party. OMB Circular A-123, Appendix B treats it as mandatory for executive agencies unless the agency obtains a waiver. The amount designated for the card issuer is paid straight to the bank; the rest reaches your account. The mechanics, with a worked split, are in paying for official travel.
Your card statement does not wait for the voucher. Payment is due 25 to 30 days after the statement closing date, and GSA SmartPay advises cardholders to file the travel claim within the FTR deadline instead of waiting for the monthly statement. A claim filed in the first few days after the trip gives the agency's 30 days the best chance of finishing before the card due date. A late claim makes the overlap more likely, and overlap is where late charges and delinquency start.
If the agency is the one that is late, the card late-charge equivalent exists for exactly that situation. You still have to pay the bill on time; the extra amount compensates you for what the delay could have cost.
If an item is disallowed
An agency may disallow an item that is not properly itemized, lacks a required receipt or other supporting documentation, or was not authorized. When it disallows part of a claim, it must pay the undisputed portion, give you a detailed explanation of the disallowance, and tell you how to appeal, what its appeal process is and when it will decide.
You may request reconsideration when you have additional facts or documentation. To do that, file a new claim that fully itemizes the items you are reclaiming, include required receipts the agency does not already have, attach a copy of the notice of disallowance, cite the proper authority if you think the agency misapplied a law or regulation, and follow your agency's own procedure.
If the claim is still denied after agency reconsideration, you may ask the Civilian Board of Contract Appeals (CBCA) to decide it under 48 CFR part 6104. The request is a written, signed claim in no particular form. It states the basis and the amount, gives your contact details and those of the agency employee who denied the claim, and attaches a copy of the denial. It is filed with the Clerk of the Board, and the Board's rules call for electronic filing. The agency responds within 30 calendar days after docketing, you may reply within 30 calendar days after receiving that response, and either side may ask for reconsideration, which the Board must receive within 30 calendar days after the decision is issued. The Board applies the statutory time limits on claims against the government, including the general six-year limit.
One rule is worth knowing before any dispute. An employee who attempts to defraud the government forfeits reimbursement and may face a fine of up to $10,000, imprisonment of up to 5 years, or both. Honest errors are corrected through the process above; inflating a claim is a different matter.
Checklist before you press submit
- Confirm the deadline: 5 working days after the trip or travel period ends, every 30 days or less on continuous travel, or your agency's shorter limit.
- Attach every lodging receipt and every receipt for an item over $75; group telephone, transit and parking meter charges only if no single item exceeds $75.
- Enter the TDY arrival and departure dates and any leave, by type and hours for each day.
- State any reduced lodging or M&IE rate from the authorization and attach special approvals.
- Mark meals provided by the government or included in a registration fee so the deduction is applied (see provided meals).
- Account for any travel advance and any unused or refunded ticket.
- Designate the split disbursement amount for card charges if your system asks for it.
- Save the submission confirmation and note day 30 and day 31 on your calendar.
- If payment is late, check that the fee, and any card late-charge equivalent, is included.
The per diem side of the claim is easier to check with a day-by-day schedule like the one in the lodgings-plus method, and the trip calculator produces one you can download. The schedule supports the arithmetic; it does not replace receipts or the authorization.
A few questions are worth asking your travel office once instead of on every trip: whether the agency sets a deadline shorter than 5 working days, how it counts working days for compressed schedules, which late fee method it uses (Prompt Payment interest or a flat fee), and whether the travel system keeps receipt images for the full 6-year retention period.
Common questions
Is there a fine for submitting a travel voucher late?
The FTR sets no fee or fine for a late claim. The practical risks lie elsewhere: your card bill still comes due, and an agency can collect undisputed delinquent card amounts from your pay without reimbursing you first if you missed the filing deadline without extenuating circumstances. Your agency may also have its own administrative rules.
Does the 30-day payment deadline count weekends and holidays?
Yes. The payment deadline is counted in calendar days, so weekends and holidays count. The separate seven-day deadline for telling you about errors in the claim is counted in working days.
Do I have to ask for the late payment fee?
The FTR states the fee as an entitlement when payment is late and does not describe a separate application. If a late payment arrives without it, ask the finance office to compare the date your proper claim reached the approving official with the payment date.
Is the late payment fee taxable income?
The interest-type fee is not reported as W-2 wages; the IRS treats it as being in the nature of interest. The extra amount equal to a card late charge is reported as additional W-2 wages. How to report either on your return is a question for a tax adviser.
I am on a three-month assignment. Can I file one claim at the end?
No. In continuous travel status the FTR requires claims at most every 30 days, and your agency may require a shorter cycle. With periodic claims the agency may also pay each interim voucher in full and deduct any advance only from the final one.
Do these deadlines apply to relocation claims?
Only in part. The claims rules sit in the TDY chapter of the FTR, and the 30-day payment rule expressly excludes nine relocation allowances, including household goods shipment, temporary quarters subsistence expenses and residence transactions. The FTR does not spell out how the 5-working-day filing deadline applies to relocation claims, so use chapter 302 and your agency's relocation office for those.
References
- 41 CFR part 301-52 — Claiming reimbursement (current text) (eCFR, Office of the Federal Register)
- 41 CFR part 301-52 as in effect on December 7, 2025 (former numbering) (eCFR, Office of the Federal Register)
- 41 CFR part 301-71 — Agency travel accountability requirements (eCFR, Office of the Federal Register)
- 41 CFR part 301-51 — Paying travel expenses (§301-51.202, travel advances) (eCFR, Office of the Federal Register)
- 41 CFR part 301-76 — Collection of undisputed delinquent travel card amounts (eCFR, Office of the Federal Register)
- Federal Travel Regulation; Reorganizing and Streamlining the FTR (final rule, 90 FR 56890, December 8, 2025) (U.S. Government Publishing Office (govinfo))
- Travel and Transportation Reform Act of 1998, Pub. L. 105-264 (U.S. Government Publishing Office (govinfo))
- Prompt Payment interest rates (U.S. Department of the Treasury, Bureau of the Fiscal Service)
- 5 CFR §1315.10 — Prompt Payment late payment interest penalties (eCFR, Office of the Federal Register)
- 48 CFR part 6104 — Civilian Board of Contract Appeals: travel and relocation expense claims (eCFR, Office of the Federal Register)
- 31 U.S.C. 3702 — Authority to settle claims (U.S. Government Publishing Office (govinfo))
- Helpful hints for travel account use (GSA SmartPay)
- OMB Circular A-123, Appendix B (revised August 27, 2019): A Risk Management Framework for Government Charge Card Programs (Office of Management and Budget)
General information, not legal or tax advice. Your travel authorization, your employer’s policy or a tax adviser decides your own case. Tell us if something here is wrong.